1.
INTRODUCTION
The chapter briefly
outlines the general
technical requirements of the
important equipment generally installed in EHV sub-stations.
2 CIRCUIT BREAKERS
Circuit Breaker is a switching
device capable of making, carrying and breaking currents under
normal circuit conditions and also
making, carrying for a specified time breaking currents under short circuit
conditions. Circuit breakers
of the types indicated below are being presently used in India.
Table- 1
36 kV |
- Minimum oil,
Vacuum and Sulphur
hexa fluoride (SF6) |
72.5 kV |
- Minimum oil,
Air blast and Sulphur hexa
fluoride (SF6) |
145 kV and
245 |
- Minimum oil, Air blast
and Sulphur hexa
fluoride (SF6) |
420 kV |
- Minimum oil,
Air blast and Sulphur hexa
fluoride (SF6) |
800 kV |
- Sulphur
hexa fluoride (SF6) |
(a)
Rated Operating Sequence
(Duty Cycle)
The operating sequence denotes the sequence of Opening and Closing operation
which the breaker can perform.
The, operating mechanism
experiences severe mechanical stresses during the auto re-closure duty. The circuit
breaker should be able to perform the operating sequence as below.
(i)
O-t-CO-T-CO
CO - Closing followed by
opening
t - 0.3 Sec. for rapid or auto re-closures T - 3 minutes
(ii)
CO-t - CO where t = 15 sec. for circuit breaker not to be used for auto-reclosure
Table 2
Rated voltage (kV) |
Rated short circuit breaking current (kA) |
Rated normal current (Amp.) |
|||||||
36 |
8 |
630 |
|
|
|
|
|
|
|
12.5 |
630 |
|
1250 |
|
|
|
|
|
|
16 |
630 |
|
1250 |
1600 |
|
|
|
|
|
25 |
|
|
1250 |
1600 |
|
2500 |
|
|
|
40 |
|
|
1250 |
1600 |
|
2500 |
|
|
|
72.5 |
12.5 |
|
800 |
1250 |
|
|
|
|
|
16 |
|
800 |
1250 |
|
|
|
|
|
|
20 |
|
|
1250 |
1600 |
2000 |
|
|
|
|
31.5 |
|
|
|
1600 |
2000 |
|
|
|
|
145 |
12.5 |
|
800 |
1250 |
|
|
|
|
|
20 |
|
|
1250 |
1600 |
2000 |
|
|
|
|
25 |
|
|
1250 |
1600 |
2000 |
|
|
|
|
31.5 |
|
|
1250 |
1600 |
2000 |
|
|
|
|
40 |
|
|
|
1600 |
2000 |
|
3150 |
|
|
245 |
20 |
|
|
1250 |
|
|
|
|
|
31.5 |
|
|
1250 |
1600 |
2000 |
|
|
|
|
|
40 |
|
|
|
1600 |
2000 |
|
3150 |
|
420 |
31.5 |
|
|
|
1600 |
2000 |
|
|
|
40 |
|
|
|
1600 |
2000 |
|
3150 |
|
|
50 |
|
|
|
|
2000 |
|
3150 |
4000 |
|
63 |
|
|
|
|
|
|
3150 |
4000 |
|
800 |
40 |
|
|
|
|
2000 |
|
3150 |
|
(b)
Total Break Time (As per IEC: 62271-100)
72.5 KV |
60 ms to 100 ms |
145 Kv |
60 ms to 100 ms |
245 kV |
Not exceeding 60 ms |
420 kV |
Not exceeding 40 ms |
800 kV |
Not exceeding 40 ms |
Pre-insertion resistor, if required shall normally have following
values. However, precise value shall be decided based
on transient over voltage studies.
420 kV |
300-450 ohms |
800 kV |
300-400 ohms |
(c)
Operating Mechanism
The circuit breaker
may be operated by anyone
of the following operating mechanisms or a combination of
them:
(a)
Pneumatically operated mechanism
(b)
Spring operated mechanism
(c) Hydraulically operated
mechanism
3.
DISCONNECT SWITCHES/ISOLATORS AND EARTHING SWITCHES
Disconnect switches are mechanical devices
which provide in their open positions, isolating distances meeting the specified
requirements. A disconnect switch can open and close a circuit when either a negligible current has to be broken or
made or when no significant change
in voltage across the terminals of each pole
of the disconnect switch occurs. It can also carry currents under normal circuit conditions and carry
for a specified time the short
circuit currents. Disconnect switches are used for transfer of load from one bus to another and also to
isolate equipment for maintenance.
The location of disconnect switches in substations
affects not only the substation
layouts but maintenance of the disconnect contacts
also. In some substations, the disconnect switches are mounted
at high positions. Although such substations occupy smaller areas, the maintenance of disconnect switches
in such substations is more difficult and time consuming.
Earthing switch is a mechanical switching device for earthing
parts of a circuit, capable of withstanding for a specified time short-circuit currents, but not
required to carry normal rated currents of the circuit.
Various types of disconnect
switches presently being used are given below:
36 kV |
Horizontal Double Break |
72.5 kV |
Horizontal Double Break/
Center Break |
145 kV |
Horizontal Double Break/
Center Break |
245 kV |
Horizontal Double Break/
Center Break |
420 kV |
Horizontal Center Break/Pantograph, Double Break |
800 kV |
J Vertical Break |
4.
INSTRUMENT TRANSFORMERS
Instrument transformer is device used to transfer
the current and voltage in
the primary system to values suitable for the necessary
instruments, meters, protective relays etc. They also
serve the purpose of isolating the primary system from the secondary
system.
Current transformer
may be either of the bushing type or
wound type. The bushing types are normally accommodated within the turret of main transformer and the wound types are invariably separately mounted. The location of the current
transformer with respect to associated circuit breaker has an
important bearing
upon the protection scheme as well as layout
of substation.
The voltage transformer may be either of the electro- magnetic type or the capacitor type. The
electro-magnetic type VTs are
commonly used where higher accuracy is required as in the case of revenue metering. For other applications capacitor type is preferred particularly at voltages
above 132 kV due to lower cost and it
also serves the purpose of a coupling capacitor for the carrier equipment. For ground fault relaying, an
additional core or a winding is
required in the VTs which can be connected in
open delta. The voltage transformers
are connected on the feeder
side of the circuit breaker. However, another set of voltage transformer is normally required
on the bus-bars for synchronization.
Typical ratings for instrument transformers normally
used are given
below: (a) Current Transformer
1 |
Nominal system voltage |
765 kV |
400 kV |
220 kV |
132 kV |
66 kV |
33 kV |
||
2. |
Highest system voltage |
800 kV |
420 kV |
245 kV |
145 kV |
72.5 kV |
36 kV |
||
3. |
Frequency |
50 Hz |
50 Hz |
50 Hz |
50 Hz |
50 Hz |
50 Hz |
||
4. |
Basic insulation level (kV peak) |
2100 |
1425 |
1050 |
650 |
330 |
170 |
||
5. |
Power frequency withstand strength |
830 |
630 |
460 |
275 |
140 |
70 |
||
6. |
Rated primary current |
3000- 2000- 1000 A |
2000- 1000- 500 A |
800A/ 600A |
800A/ 600A |
400A/ 200A/ |
800A/ 400A/ 200A |
||
7. |
Rated burden for metering |
20 VA |
20 VA |
20 VA |
20 VA |
20 VA |
20 VA |
||
8. |
Rated short time current for 1 sec. |
40kA |
40 kA |
40 kA |
31.5 kA |
31.5 kA |
25 kA |
||
9. |
Secondary current amps. |
1 |
1 |
1 |
1 |
1 |
1 |
||
10. |
No. of cores |
5 |
5 |
5 |
3 |
3 |
3 |
||
11. |
Maximum temperature rise over design ambient temp |
As per IEC : 60044-1 |
|||||||
12. |
Type of insulation |
Class A |
|||||||
13. |
Instrument safety factor |
<10 |
<10 |
<10 |
<10 |
<10 |
<10 |
<10 |
|
14. |
Class of accuracy (a)
Metering Core (b)Protection Core |
0.2 3P |
0.2 3P |
0.2 3P |
0.2 3P |
0.2 3P |
0.2 3P |
0.2 3P |
|
(b)
Voltage Transformers
1. |
Type |
Single phase,
oil filled, Natural
oil cooled |
|||
2. |
Nominal system
voltage |
220 kV |
132 kV |
66 kV |
33 kV |
3. |
Highest system
voltage |
245 kV |
145 kV |
72.5 kV |
36 kV |
4. |
Insulation leve (a) Rated one min. Power Frequency withstand Voltage kV (rms) HV Terminal to earth |
460 |
275 |
140 |
70 |
|
(b) Impulse withstand voltage
(1.2/50 micro sec.
wave shape) kV (Peak) |
1050 |
650 |
325 |
170 |
5. |
Over voltage factor (a) Continuous (b) 30 sec. |
1.2 1.5 |
1.2 1.5 |
1.2 1.5 |
1.2 1.5 |
6. |
No. of secy. winding |
Three |
Three |
Three |
Three |
7. |
Voltage ratio |
220 kV/ 3 |
132kV/3 |
66 kV/ 3 |
33 kV/ 3 |
110 V/ 3 |
110 V/ 3 |
110 V/ 3 |
110 V/ 3 |
||
8. |
Rated burden (not less than) (a) Core I (Metering) (b) Core II (Protection) (c) Core III (Open Delta |
100/50 VA 100/50VA 100/50 VA |
100/50VA 100/50VA 100/50VA |
100/50VA 100/50VA 100/50VA |
100/50VA 100/50VA 100/50VA |
9. |
Connection |
Y/Y/open
delta |
|||
10. |
Class of accuracy |
||||
(a) Core I (Metering) |
0.2 3P 3P |
0.2 3P 3P |
0.2 3P 3P |
0.2 3P 3P |
|
(b) Core II (Protection) |
|||||
(c) Core III (Open Delta) |
(c)
Capacitor Voltage Transformer
Voltage |
765 kV |
400 kV |
220 kV |
132 kV |
Transformation ratio |
765√ 3 kV 110/√3V |
400√3 kV 110/√3V |
220√3 kV 110/√3V |
132√3 kV 110/√3V |
No. of secondary winding |
3 |
3 |
3 |
3 |
Voltage factor |
1.2 Continuous &
1.5 for 30 seconds |
|||
Rated capacitance |
4400/8800 pF |
4400 PF/8800 pF |
4400 pF |
4400 pF |
Rated burden |
50 VA |
100 V A/50
VA |
IOOVA/50 VA |
100 V A/50 VA |
Insulation Level (a) Rated one minute power frequency with stand voltage kV (rms) |
830 |
630 |
460 |
275 |
(b) Impulse withstand voltage (1.2/50) micro
second wowe shaped
kV (Peak) |
2100 1550 |
1425 1050 |
1050 - |
650 - |
(e) Switching Impulse
withstand voltage (250/2500 Microv micro secs |
1550 |
1050 |
- |
- |
Class of accuracy (a) Core I (Metoring) (b) Core 11(Protection) (e) Core III (open Delta) |
0.2 3P 3P |
0.2 3P 3P |
0.2 3P 3P |
0.2 3P 3P |
5.
TRANSFORMERS
General technical
requirements of the transformers presently
being used are given below:
33 kV Power Transformers
Three Phase Rating MV A |
Voltage Ratio |
Cooling |
1.0 |
33/11 |
ONAN |
1.6 |
33/11 |
ONAN |
3.15 |
33/11 |
ONAN |
4.0 |
33/11 |
ONAN |
5.0 |
33/11 |
ONAN |
6.3 |
33/11 |
ONAN |
8.0 |
33/11 |
ONAN |
10.0 |
33/11 |
ONAN |
Vector Group: Dyll
66 kV Power
Transformers
Three Phase Rating MV A |
Voltage Ratio |
Cooling |
6.3 |
66/11 |
ONAN/ONAF |
8.0 |
66/11 |
ONAN/ONAF |
10.0 |
66/11 |
ONAN/ONAF |
12.5 |
66/11 |
ONAN/ONAF |
20.0 |
66/11 |
ONAN/ONAF |
Vectcr Group: YyO
145 kV Power Transformers
Three
Phase Rating
MVA |
Voltage Ratio |
Impedance Voltage
(Percent) |
Cooling |
Two Winding |
|
|
|
20 |
132/33 |
10 |
ONAN/ONAF |
40 |
132/33 |
10 |
ONAN/ONAF |
Vector Group: YNynO or YNdl1
245 kV Power Transformers
(A)Two Winding |
|||
|
|
|
ONAN/OF AF |
50 |
220/66 kV |
12.5 |
or ONAN/ODAF |
|
|
|
ONAN/OF AF |
|
|
|
or ONAN/ODAF |
|
220/66 kV |
12.5 |
ONAN/OFAF |
100 |
|
|
or ONAN/ODAF |
100 |
220/33 kV |
15.0 |
|
(B) Interconnecting Auto Transformers |
|||
35,50 |
220/33 |
10 |
ONAN/ONAF ONAN/ONAF ONAN/ONAF/OF AF Or ONAN/ONAF/ODAF ONAN/ONAF/ODAF or ONAN/ONAF/ODAF ONAN/ONAF/OF
AF or ONAN/ONAF/ODAF |
50 |
220/132 |
10 |
|
100 |
220/1 32 |
12.5 |
|
160 |
220/132 |
12.5 |
|
200 |
220/1 32 |
12.5 |
Vector Group: YNaodl1
Auto Transformers (420 kV voltage
level) (Constant Percentage Impedance)
Three-Phase HV/IV/LV |
Voltage Ratio |
Tapping Range percent |
Per Cent |
Impedance |
Voltage |
Cooling |
MVA |
|
|
HV-IV |
HV-LV |
IV-LV |
|
100/1 00/33.3 |
400/132/33 |
+ 10% to -10% 16 steps
of 1.25% |
12.5 |
27 |
12 |
ONAN/ONAF |
200/200/66.7 |
400/132/33 |
+10% to -10% 16 steps
of 1.25% |
12.5 |
36 |
22 |
ONAN/ONAF Or ONAN/ONAF |
250/250/83.3 |
400/220/33 |
+10% to -10% 16 steps of 1.25% |
12.5 |
45 |
30 |
ONAN/ONAF Or ONAN/ONAF |
315/315/1 05 |
400/220/33 |
+10% to -10% 16 steps
of 1.25% |
12.5 |
45 |
30 |
ONAN/ONAF Or ONAN/ONAF |
500/500/166.7 |
400/220/33 |
+10% to -10% 16 steps of 1.25% |
12.5 |
45 |
30 |
ONAN/ONAF Or ONAN/ONAF |
630/630/210 |
400/220/33 |
+ 10% to -10% 16 steps
of 1.25% |
12.5 |
45 |
30 |
ONAN/ONAF Or ONAN/ONAF |
Vector Group: YNaodll
Auto Transformers (800 kV voltage level)
Ratings |
||||||
Three
phase rating HV/IV/LV MVA |
Voltage Ratio kV |
Tapping range (Percent) |
Percent |
Impedanc e |
Voltage |
Cooling |
HV/IV |
HV/LV |
IV/LV |
|
|||
315/315/105 |
765/220/33 |
+4.5% -7.5% 24 steps |
12.5 |
40 |
25 |
ONAN/OFAF
or ONAN ODAF or ODAF |
630/630/210 |
765/400/33 |
-do- |
12.5 |
60 |
40 |
-do- |
750/750/250 |
-do- |
-do- |
-do- |
-do- |
-do- |
-do- |
1000/1 000/333.3 |
-do- |
-do- |
14.0 |
65 |
45 |
-do- |
1500/1500/500 |
-do- |
-do- |
-do- tolerance |
-do- ±10% |
-do- ±15% |
-do- ±15% |
Vector Group: YNaodll
6 PROTECTION AGAINST
LIGHTNING
A substation has to be shielded against direct
lightning strokes either by provision
of overhead shield wire/earthwire or spikes (masts).
Typical technical parameters adopted
for surge arrestors are as
follows:
Sl.No. |
Item |
765 kV |
400 kV |
220 kV |
132 kV |
66 kV |
1. |
System voltage kV |
765 |
400 |
220 |
132 |
66 |
2 |
Highest system voltage
kV |
800 |
420 |
245 |
145 |
72.5 |
3. |
Rated voltage
Arrestor kV |
624 |
390/360/336 |
198/216 |
120 |
60 |
4. |
Nominal discharg current |
20kA |
----------------10kA----------- |
|||
5. |
Class |
Class 5 |
Class 3 |
Class 3 |
Class 3 |
|
6. |
Pressure relief class |
--------------------A-------------------- |
||||
|
7.
INSULATORS
The creepage distances
for the different pollution levels
are provided according
to the following table:
Pollution level |
Creepage distance (mm/kV) |
Light |
16 |
Medium |
20 |
Heavy |
25 |
Very Heavy |
31 |
For determining the creepage distance
requirement, the highest line-to-line voltage
of the system forms the basis.
The following types of insulators are normally used:
(A)
Support Insulators:
(i)
Cap and pin type
(ii)
Solidcore type
(iii)
Polycone type
(B)
Strain Insulators:
(i) Disc insulators
(ii) Long rod porcelain insulators
(iii)
Polymer insulators
8.
PROTECTION
(A)
Line Protection
(i)
400 kV Lines
Generally two independent high speed main protection schemes
called Main-I and Main-II with atleast one of them being
carrier aided non-switched three zone distance protection are adopted. The other protection may be a phase segregated current differential (this may require
digital communication) phase comparison, directional comparison
type or a carrier aided non-switched distance
protection. Further, if Main-I
and Main II are both distance protection schemes, then they should
be preferably of different type. However, they need not necessarily be of different make. Both the protections should be suitable for single and three phase
tripping. In addition to the above following shall also be provided:
(i)
Two stage over-voltage protection.
(ii)
Auto reclose relay suitable for I ph/3 ph reclosure.
(iii)
Sensitive IDMT directional Overcurrent E/F relay.
(ii) 220 k V Lines
There should be atleast one
carrier aided non-switched three zone
distance protection scheme. In addition to this another non-switched/switched distance scheme or directional over current and earth fault relays should be provided as back up. Main
protection should be suitable for single and three phase tripping. Additionally, auto-reclose relay
suitable for I ph/3 ph (with
dead line charging and synchro check facility) reclosure shall be provided.
In case of
both line protections being Distance Protections, IDMT type E/F relay shall also be provided additionally.
(B)
Bus bar Protection
Bus bar protection is required to be provided for high speed
sensitive clearance of bus bar faults by tripping all the circuit
breakers connected to faulty bus.
(C)
Transformer Protection
Generally following protective and monitoring equipment for transformers of
400 kV and 220 kV class are provided:
(i)
Transformer differential protection
(ii)
Overfluxing protection
(iii)
Restricted earth-fault protection
(iv)
Back-up directional O/C + E/F protection on HV side
(v)
Back-up directional O/C + E/F protection on LV side
(vi)
Protection and monitors built in to Transformer (Buchholz relay, Winding and Oil
Temperature Indicators, Oil Level Indicator, OLTC Oil Surge Relay and Pressure
Relief Device)
(vii)
Protection for tertiary
winding
(viii)
Overload alarm
(ix)
Circulating current Differential Protection (Inter-turn phase fault)
(D)
Local Breaker
Back-up Protection
In the event of any circuit breaker failing to trip on
receipt of trip command from protection relays,
all circuit breakers
connected to the bus section to which the faulty circuit breaker is connected
are required to be tripped
with minimum possible
delay through LBB protection.
All protections need to be tested
periodically for functional operation and record
of testing should be provided
in the substation for future records.
9.
CLEARANCES
Minimum clearances required for substation
upto 800 kV voltage level are as follows:
Highest system voltage (kV) |
Basic Insulation level (kVp) |
Switching impulse voltage (kVp) |
Minimum
clearances $ |
Sectional clearances (mm) |
|
|
|
|
Between Phase And Earth
(mm) |
Between Phases
(mm) |
|
36 |
170 |
- |
320 |
320 |
2800 |
72.5 |
325 |
- |
630 |
630 |
3000 |
145 |
550 650 |
- |
1100 1300 |
1100 1300 |
4000 4000 |
245 |
950 1050 |
- |
1900 2100 |
1900 2100 |
4500 5000 |
420 |
1425 |
1050 |
3400* |
- |
6500 |
|
|
(Ph-E) 1575 (Ph-Ph) |
- |
4200** |
|
800 |
2100 |
1550 (Ph-E) 2550 (Ph-Ph) |
6400* |
9400** |
10300 |
* Based on Rod-structure air gap.
** Based on Rod-Conductor air gap.
$ These
values of air clearances are the minimum values dictated by electrical consideration and do not include any
addition for construction
tolerances, effect of short circuits, wind effects and safety of personnel, etc.
10.
Earthing
Provision of adequate
earthing system in a substation is extremely important
for safety of the operating personnel as well as for proper system operation and performance of the protection devices. The primary requirements of a good earthing system in a substation are:
(a)
The impedance to ground should be as low as possible. In the substations with high fault levels, it should not exceed 1 ohm
and in the substations with low fault levels it should not exceed 5 ohms.
(b)
The step and touch potentials should be within
safe limits.
To meet these requirements,
an earthing system comprising an
earthing mat buried at a suitable depth below ground, supplemented with ground rods at suitable points is
provided in the substation. The non-current-carrying
parts of all the equipment in the substation and neutral of the transformer are connected to that earthing mat so
as to ensure that under fault
conditions, none of these parts is at a potential higher than that of the earthig mat. The ground rods are helpful
in maintaining low value of
resistance which is particularly important for
installations with high system earth fault currents.
All substations should have provision
for earthing the following:
(a)
The neutral points of equipment
in each separate system. There should be independent earth for the
different systems. Each of these earthed
points should be interconnected with the station earthing
mat.
(b)
Equipment framework and other non-current carrying parts.
(c)
All extraneous metal framework not associated with equipment.
(d)
Surge arresters: These should have independent earthing
which should in turn be connected to the station grounding grid or earthmat.
Switchyard areas are usually
covered with about 10 cm of gravel or
crushed rock which increases the safety of personnel against shocks, prevents the spread of oil
splashes and aids in weed control. This
entails the provision of service roads for movement of vehicles required
for carrying the equipment from the switchyard to service bay and back.
Bare stranded copper conductor or copper strip found extensive application in the construction of earth mat in the past. However on account of high cost of
copper and the need to economies in
the use of copper, current practice in the country is to use mild steel conductor for earth mat.
11.
Fire Fighting
System
All substations should be equipped
with fire fighting
systems conforming to the requirements
given in IS: 1646-1982 and Fire Protection Manual Part-I issued by Tariff Advisory Committee
of Insurance Companies.
The more valuable equipment or areas forming
concentrated fire risk should be covered by special fire protective systems.
In this class are:
(a)
Transformers, both indoor and outdoor;
(b)
Oil-filled reactors;
(c)
Oil-filled switchgear;
(d)
Oil tanks and oil pumps;
(e)
Oil, grease and paint stores and
(f)
Synchronous condensers.
Although the replacement of bulk-oil and minimum oil circuit
breakers by vacuum type and SF6 gas circuit breakers has reduced the risk of fires in electrical installations,
considerable risk still exists on
account of transformers, reactors, cables etc. which contain combustible insulating materials. It is therefore
necessary to provide efficient Fire Protection Systems
in the Electrical Installations. Fire Protection System consists of the following:
(i)
Fire 'Prevention
(ii)
Fire Detection & Annunciation
(iii)
Fire Extinguishing
(i)
Fire
Prevention
Fire prevention is of utmost importance and should be
given its due if risk of occurrence of fires has to be eliminated/minimized. The safety and preventive measures
applicable for substations as recommended
by the relevant authorities must be strictly followed while planning the substations.
All fire fighting equipment and system should be
properly maintained. Regular
mock drills should be conducted
and sub station staff made aware of importance of fire protection and imparted training
in proper use of the fire fighting
equipment provided in substation I control room.
(ii)
Fire Detection
and Annunciation
Fire detection if carried out
at the incipient stage can help in timely containment and extinguishing of the fire speedily. Detection can either be done visually by
the personnel present in vicinity of
the site of occurrence or automatically with the use of detectors operating on the principles of fixed temperature resistance variation, differential thermal expansion, rate of
rise of temperature, presence of
smoke, gas, flame etc. Fire detectors of the following
type are usually used:
(i)
Ionization type
(ii)
Smoke type
(iii)
Photoelectric type
(iv)
Bimetal type
(v)
Linear heat Detection
type/Quartzoid bulb type
(iii) Fire Extinguishing
The Fire Extinguishing Systems used for fire protection of the various
equipments /building in substations are the following:
(i)
Hydrant System
(ii)
High Velocity Water Spray
System
(iii)
Portable Fire Extinguishers
(iv)
Fire Buckets.
(a)
Hydrant System
This type of Fire Protection System
is provided for Buildings.
The system consists
of a network of laid MS Pipes fed from storage tank and water hydrant outlets
provided at suitable
locations. Fire fighting canvas pipes are provided in appropriate cabinets near the hydrants which can be
accessed by breaking the glass of the
storage unit. The canvas pipes are connected to the hydrants and water can be sprayed on the fire after opening the valve of the hydrant.
(b)
High Velocity Water
(HVW) Spray System
This type of Fire Protection System
is provided for the following
types of equipment:
(i)
Power Transformers, both auto and multi-winding
(ii)
Shunt Reactors
This system is designed
on the assumption that one reactor/transformer is on fire at a time.
For this assumption, the largest piece of equipment
forms the basis.
(c)
Portable Fire Extinguishers
The portable fire extinguishers are strategically placed in the control
room as well as the switched for easy accessibility and are used for extinguishing small fires
or fires in a restricted area.
The following types of portable fire extinguishers are normally used.
(i)
Chemical Foam type
(ii)
Mechanical Foam type
(iii)
Dry Powder cartridge
type
(iv)
Carbon Dioxide type.
Fire Buckets
These are specially fabricated buckets which filled with river sand and kept in the substation on stands.
These buckets are provided with an
additional handle on the side so that the sand can be easily sprayed
on the fire.
These buckets
are used for extinguishing fires on the ground.
Water
Supplies
Water for fire fighting purposes should be supplied from the water storage tanks meant exclusively for the
purpose. The aggregate storage
capacity of these tanks should be equal to the sum of the following:
(i)
One-hour pumping capacity
of Hydrant System or 135 cum whichever
is more
(ii)
Half-an-hour water requirement for single largest
risk covered by HVW Spray System.
Instrumentation
and Control
HVW Spray System should include
suitable instrumentation and necessary controls
to make the system efficient and reliable. There should be
local control panels for each of the
pumps individually as also for the operation of deluge valve of the HVW Spray System. There should be a
common control panel for the Jockey Pump and Air Compressors. Main annunciation
panel should be provided in the control room with provision for
repeating some annunciation from the
pump house.
A diesel engine operated water pump is also provided
for back-up in case electrically operated motor-pumps fail due to interruption in electricity supply.
Filtration/Hot Oil Circulation
·
Connect bottom filter
valve of tank to inlet point of filter
machine.
·
Connect top filter valve
of tank to outlet of vacuum filter machine and start oil circulation
·
The filter outlet
temperature should be limited to 60 ~ 700 C.
·
Continue filtration for 4 cycles whole oil should be
circulated 4 times.
·
Oil circuit should include a vacuum chamber in which
oil drawn from the transformer is
sprayed and the moisture and gases are released from the oil are extracted
by the vacuum pump.
·
Oil drawn from transformer is passed through a filter
press before being admitted to the vacuum
chamber to remove impurities.
·
A minimum capacity of 6000 litres per hour is
recommended for the circulation equipment.
·
Cooler connection at inlet shall be kept closed to minimize loss of temperature during circulation.
Outlet valve shall be kept open to allow expansion of oil inside the cooler.
·
Coolers also shall be included
in the hot oil circulation towards the end of the process.
·
Drain the oil by simultaneously admitting dry air or nitrogen gas from the top.
This is to avoid
winding insulation coming
in contact with moisture.
·
Apply vacuum of 1.0 torr or better and maintain for 12
Hrs. (1 mm of Hg)
·
Inject oil under vacuum upto a level of approximately
half of the conservator.
·
Repeat vacuum/hot oil circulation cycle till required
dryness is obtained. The oil
temperature shall not increased more than 750 C in any case.
·
Normally 3 or 4 cycles of hot oil circulation and
evacuation will be sufficient to
obtain the required dryness for the insulation.
·
Dryness of insulation is determined by measuring
insulation resistance of transformer winding.
·
Insulation resistance between each pair of windings and
also between windings and earth shall
be measured by using a 2000 V megger. Readings
shall be comparable with the
factory test results.
·
Direct heating of transformer is not recommended for
drying out at site.
·
Oil samples shall be tested for moisture
content, (below 20/15/10 ppm for 145/220/400 KV class
respectively). Break down voltage
(more than 60 KV at 2.5 mm gap). Resistivity
( > 1012 ohm meter) before final oil filling.
·
Do not measure insulation resistance when the
transformer is under vacuum.
Note : As the temperature of oil rises
the megger value drops down upto
minimum value and after remaining some hours at minimum value when it
starts rising again then it should be understood as the circulation/filtration is complete.
TEMPERATURE OF OIL (0C)
Variation of Insulation Resistance with Temperature
Dielectric Strength of Insulating Oil (12.5mm dia. Spheres, 2.5 mm gap)
No. |
Nominal Voltage of Transformer |
Dielectric Strength of Insulating Oil (KV) |
1. |
145 KV class
and above |
More than 50 |
2. |
72.5 KV class to less than 145 KV |
More than 40 |
3. |
Less than 72.5
KV class |
More than 30 |
Acid Content of Insulating Oil (By neutralization)
No. |
Judgment |
Acid Content of Oil (mg KOH/g) |
1. |
Good |
Less than 0.2 |
2. |
Replace or do filtrations |
0.3 ~ 0.5 |
3. |
Replace immediately |
Above 0.5 |
Resistivity of Insulating Oil
No. |
Judgment |
Resistivity of oil at 900 C (Ω - cm) |
1. |
Good |
More than 0.1 x 10 12 |
2. |
Fair |
1 x 10 11 to 0.1 x 10 12 |
3. |
Poor |
Less than 0.1 x 10 11 |
Water Content
No. |
Nominal Voltage
of Transformer |
Water Content
(ppm) |
1. |
145 KV class
and above |
20 ppm max. |
2. |
Below 145 KV class |
40 ppm max. |
Dielectric Dissipation Factor
No. |
Nominal Voltage
of Transformer |
At 900 C, 40 ~ 60 Hz |
1. |
145 KV class
and above |
0.2 max. |
2. |
Below 145 KV class |
1.0 max. |
Oil Handling Capacity
Rating of Filtering Machine
No. |
Rating of T/F |
Capacity of oil
in T/F Kilo Litre |
Oil handling Capacity of machine Ltr./hr |
1. |
5/8 MVA 33/11 KV |
3/5 |
1000 Ltr/hr. |
2. |
20/40 MVA 132/33 KV |
18/20 |
4000 Ltr/hr. |
3. |
100/160 MVA 220/132 KV |
45/50 |
6000 Ltr/hr. |
4. |
240/315 MVA 400/220 KV |
70/90 |
6000 Ltr/hr. |