Pre - Commissioning Check List For Final Distribution Board.

 



Pre - Commissioning Check List                                                                    For Final Distribution Board.

MEP Contractor 






Locatio / Area      :

Verification Sign-off

Feeder SMP Ref :

 

 

 

 

 

 

S.No.

Activities / Items to be Inspected

Engineer

QCI

1

Verify the Installed DB's have approved submittals.

 

 

2

Ensure the drawings used for installation are correct and approved.

 

 

3

Check and ensure the DB's new and undamaged.

 

 

4

Check the DB's as per approved load schedule and drawings.

 

 

5

Check the Nameplate and identification labels as per Load schedule and approved sumittals.

 

 

6

Check the DB's have rigid support.

 

 

7

Ensure location of DB's is as per approved drawing.

 

 

8

Check the termination and dressing of cables and wires completed neatly.

 

 

9

All cables and wires including grounding are terminated and identified.

 

 

10

Ensure all terminals are tightened as required.

 

 

11

Ensure DB's interiors are cleaned and free from dust.

 

 

12

Check the grounding has been provided as per approved drawing including the body of the DB's.

 

 

13

Identification provided as specified / required.

 

 









Comments / Remarks, if any

 

 

 

ETA - QA/QC Engineer

Signature :

 

 

Name      :

 

 

Date        :

 

 

 

*