Installation Check List For ATS |
MEP Contractor |
|
|
|
Locatio / Area : |
Verification Sign-off |
||
|
|
|
|
|
|
S.No. |
Activities / Items to be Inspected |
Engineer |
QCI |
|
1 |
Verify the installed ATS have approved submittals. |
|
|
|
2 |
Ensure the drawings used for installation are correct and approved. |
|
|
|
3 |
Check and ensure the ATS are new and undamaged. |
|
|
|
4 |
Factory test reports received and verified. |
|
|
|
5 |
Check the ATS as per approved drawings. |
|
|
|
6 |
Check the Name Plate and Identification labels. |
|
|
|
7 |
Check the mounting channels are even and free from any damage. |
|
|
|
8 |
Check all meters, indication lamp, handles and locks are correct and undamaged. |
|
|
|
9 |
Ensure adequate clearance available around ATS as required and as per drawings and regulations. |
|
|
|
10 |
Check the termination and dressing of cables completed neatly. |
|
|
|
11 |
Esure all terminals are tightened as required. |
|
|
|
12 |
Ensure ATS are cleaned and free from dust and small metallic particles. |
|
|
|
13 |
Check the grounding has been provided as per approved drawing including the body and door of the panel. |
|
|
|
14 |
Check the Identification and warning signs provided as specified / required. |
|
|
|
15 |
Submit the consultant Inspection request. |
|
|
|
Comments / Remarks, if any |
|||
|
|
|||
|
|
|||
|
|
ETA - QA/QC Engineer |
||
|
Signature : |
|
|
|
|
Name : |
|
|
|
|
Date : |
|
|
|