1 |
Check the Material is as per approved submittal. |
|
|
|
2 |
Check drawings used for installation are latest and approved. |
|
|
|
3 |
Check all material are new and undamaged. Megger each length of busway before installation to check for possible damage of contamination during shifting and storage. |
|
|
|
4 |
Check the layout, opening and elevations of the installed bus duct system as per approved drawings. |
|
|
|
5 |
Check the installation complies with the manufacturer's instruction / drawings. |
|
|
|
6 |
Check the supporting system and support spacing as the approved drawings. |
|
|
|
7 |
Check the continuity and insulation resistance prior and after the installation. |
|
|
|
8 |
Check all the nuts, bolts, screws etc. are tight and secure. ( Torque 60-80 lbs) |
|
|
|
9 |
Check the installation of bus duct system is coordinate with other services as required. |
|
|
|
10 |
Check the earth bonding is provided as per approved drawings. |
|
|
|
11 |
Check all joints are tightened with totque sensitive special bolts supplied by the manufacturer using torque wrench. |
|
|
|
12 |
Manufacturer's representative to check and certify the installation, prior to consultant's inspection. |
|
|
|
13 |
Identification labeling completed as per approved details and DEWA requirement. |
|
|
|