Pre- Commissioning checks/ tests for Transformers and Reactors

Once oil filling is completed, various pre-commissioning checks/ tests are performed to ensure the healthiness of the Transformer/ Reactor prior to its energization. Various electrical tests are to be performed and their significance is given below in Table-8:

Table:8

 

Sr.

No.

Name of Test/

Check point

Purpose of test/ check

1.

Core insulation tests

Allows for investigating accidental grounds which results in circulating currents if there is more than one connection between the core and ground.

2.

Earth pit resistance measurement

To check the resistance of earth pit provided for Transformer. In case, the resistance is more, proper treatment is to be given.

3.

Insulation Resistance (IR) measurement

Test reveals the condition of insulation (i.e. degree of dryness of paper insulation), presence of any foreign contaminants in oil and also any gross defect inside the transformer (e.g. Failure to remove the temporary transportation bracket on the live portion of tap-changer part)

4.

Capacitance and Tan δ measurement of bushings

Measurement of C1 & C2 Capacitance and Tand in UST mode. Changes in the normal capacitance of an insulator indicate abnormal conditions such as the presence of moisture layer, short -circuits or open circuits in the capacitance network.

5.

Capacitance and Tan δ of windings

Dissipation factor/Loss factor and capacitance measurement of winding is carried out to ascertain the general condition of the ground and inter-winding insulation

6.

Turns ratio (Voltage ratio) measurement

To determine the turns ratio of transformers to identify any abnormality in tap changers/ shorted or open turns etc

7.

Vector Group & Polarity

To    determine    the    phase    relationship    and    polarity    of transformers

8.

Magnetic Balance test

This test is conducted only in three phase transformers to check the imbalance in the magnetic circuit

9.

Floating Neutral point measurement

This test is conducted to ascertain possibility of short circuit in a winding.

10.

Measurement of Short Circuit Impedance

This test is used to detect winding movement that usually occurs due to heavy fault current or mechanical damage during transportation or installation since dispatch from the factory.


 

11.

Exciting/Magnetisin g current measurement

To locate defect in magnetic core structure, shifting of windings, failures in turn to turn insulation or problems in tap changers. These conditions change the effective reluctance of the magnetic circuit thus affecting the current required to establish flux in the core

12.

Operational checks on OLTCs

To ensure smooth & trouble free operation of OLTC during operation.

13.

Tests/ Checks on Bushing Current Transformers (BCTs)

To ascertain the healthiness of bushing current transformer at the time of erection

14.

Operational Checks on protection System

Operational Checks on cooler bank (pumps & Fans), Breathers (Silicagel or Drycol), MOG, temperature gauges (WTI/OTI), gas actuated relays (Buchholz, PRD, SPR etc.) and simulation test of protection system

15.

Stability of Differential, REF of Transformer/ Reactor

This test is performed to check the proper operation of Differential & REF protection of Transformer & Reactor by simulating actual conditions. Any problem in CT connection, wrong cabling, relay setting can be detected by this test.

16.

Frequency Response Analysis (FRA)

measurement

To assess the mechanical integrity of the transformer. Transformers while experiencing severity of short circuit current lo ses its mechanical property by way of deformation of the winding or core. During pre-commissioning this test is required to ascertain that Transformer active part has not suffered any severe impact/ jerk during transportation.

17.

Winding resistance measurement

To check for any abnormalities due to loose connections, broken strands and high contact resistance in tap changers

18.

Dissolved Gas Analysis (DGA) of oil sample

Oil sample for DGA to be drawn from transformer main tank before commissioning for having a base data and after 24 hrs. of charging subsequently to ensure no fault gas developed after first charging. DGA analysis helps the user to identify the reason for gas formation & materials involved and indicate urgency of corrective action to be taken

 

*

Post a Comment (0)
Previous Post Next Post