Installation Check List For Generator |
MEP Contractor |
|
|
|
Locatio / Area : |
Verification Sign-off |
||
|
|
|
|
|
|
S.No. |
Activities / Items to be Inspected |
Engineer |
QCI |
|
1 |
Verify the installed Generator have approved submittals. |
|
|
|
2 |
Ensure the drawings used for installation are correct and approved. |
|
|
|
3 |
Check and ensure the Generator are new and undamaged. |
|
|
|
4 |
Factory test reports received and verified. |
|
|
|
5 |
Check the termination are in good condition. |
|
|
|
6 |
Check the labelling of Panels, Cables and their identification. |
|
|
|
7 |
Check the Earthing system for Generator. |
|
|
|
8 |
Check Fuel level. |
|
|
|
9 |
Check Fuel leakages. |
|
|
|
10 |
Check Engine oil level. |
|
|
|
11 |
Check coolant. |
|
|
|
12 |
Check Exhaust pipe work & Muffler assembly installation. |
|
|
|
13 |
Check Exhaust system leakage. |
|
|
|
14 |
Check circuit breakers and its operation. |
|
|
|
15 |
Check battery connection. |
|
|
|
16 |
Check battery charging system. |
|
|
|
17 |
Check to see that switchgear is in the auto position. |
|
|
|
18 |
Simulate power failure & check the working of auto change over system. |
|
|
|
Comments / Remarks, if any |
|||
|
|
|||
|
|
|||
|
|
ETA - QA/QC Engineer |
||
|
Signature : |
|
|
|
|
Name : |
|
|
|
|
Date : |
|
|
|