Pre-Commissioning Test Procedures for SEC Transmission Electrical Installations

Pre-Commissioning Test Procedures for SEC Transmission Electrical Installations


Pre-Commissioning Test Procedures for SEC Transmission Electrical Installations

1. Introduction

The Saudi Electricity Company (SEC) requires rigorous pre-commissioning tests for transmission electrical installations to ensure system reliability, safety, and compliance with operational standards. Pre-commissioning tests are conducted before energization to verify the integrity and functionality of electrical equipment.

This document outlines the pre-commissioning test procedures for SEC transmission electrical installations, including transformers, circuit breakers, switchgear, protection relays, and SCADA systems.


2. Scope of Pre-Commissioning Testing

The pre-commissioning phase includes the inspection and testing of:

  1. Power Transformers (132kV, 380kV, etc.)
  2. Gas-Insulated Switchgear (GIS) & Air-Insulated Switchgear (AIS)
  3. Circuit Breakers & Disconnectors
  4. Current & Voltage Transformers (CTs & VTs)
  5. Protection and Control Systems
  6. SCADA, Telecommunication, and Auxiliary Systems
  7. Grounding & Earthing Systems

All tests comply with SEC standards, IEC 61850, and IEEE testing guidelines.


3. Pre-Commissioning Test Procedures

3.1 Visual Inspection & Verification

Before conducting electrical tests, a thorough visual inspection is carried out, including:

  • Physical integrity of transformers, GIS, AIS, and switchgear
  • Verification of nameplates, rating plates, and wiring diagrams
  • Cable terminations, bolted connections, and insulation check
  • SF6 gas pressure (for GIS) and transformer oil levels
  • Earthing continuity and lightning protection

3.2 Transformer Pre-Commissioning Tests

  • Insulation Resistance (IR) Test: Ensures transformer insulation health
  • Turns Ratio (TTR) Test: Confirms voltage transformation ratio
  • Vector Group Test: Ensures correct phase alignment
  • Winding Resistance Measurement: Detects internal faults
  • Magnetic Balance Test: Identifies core issues
  • Oil Dielectric Strength Test: Ensures oil insulation quality

3.3 Circuit Breaker Testing

  • Contact Resistance Measurement: Ensures minimal resistance in breaker contacts
  • Timing Test: Measures opening/closing time to verify speed
  • SF6 Gas Pressure Test (for GIS): Ensures adequate gas insulation
  • Functional Test: Verifies tripping and closing operations

3.4 Current & Voltage Transformer Testing (CT & VT)

  • Insulation Resistance Test
  • CT Ratio & Polarity Test
  • Excitation Curve Test
  • Burden Test for CTs
  • Secondary Injection Test for VTs

3.5 Protection Relay Testing

Using secondary injection kits (OMICRON, MEGGER, etc.), protection relays are tested:

  • Overcurrent & Earth Fault Protection (OC/EF)
  • Distance Protection (for Transmission Lines)
  • Differential Protection (for Transformers & Busbars)
  • Breaker Failure Protection
  • Directional Overcurrent Protection (DOCP)
  • Synchronization Checks

3.6 GIS / AIS Switchgear Testing

  • High Voltage Withstand Test (HV Test)
  • Primary Injection Test (for CT circuits)
  • Busbar & Insulation Resistance Test
  • Functional Interlock Verification

3.7 SCADA & Communication System Testing

  • Remote Terminal Unit (RTU) Testing
  • End-to-End Testing between Substations & Control Center
  • Data Communication & Protocol Verification (IEC 61850, DNP3, etc.)
  • Alarms, Indications, and Control Functionality Tests

3.8 Grounding & Earthing System Testing

  • Continuity Test for Earthing Grid
  • Earth Resistance Measurement
  • Step & Touch Potential Testing

4. Test Equipment & Standards

The following test equipment is used for pre-commissioning:

  • Insulation Tester (Megger 5kV, 10kV)
  • OMICRON Relay Test Kit (CPC 100, CMC 356)
  • Doble Power Factor Tester (Doble M4000)
  • Transformer Turns Ratio (TTR) Tester
  • Circuit Breaker Analyzer (Doble, Megger)
  • Primary & Secondary Injection Kits
  • SF6 Gas Analyzer

All tests follow SEC, IEC 61850, IEC 60270, and IEEE 400 standards.


5. Test Results & Documentation

After completing pre-commissioning tests, a comprehensive test report is prepared, including:

  • Test procedures and observations
  • Test results with pass/fail criteria
  • Calibration certificates of test equipment
  • Photographic evidence of test setups
  • Recommendations for corrective actions (if needed)

6. Conclusion & Recommendations

The pre-commissioning tests ensure that all electrical installations in SEC transmission networks are safe, reliable, and ready for energization. Successful testing minimizes risks, prevents failures, and guarantees smooth grid integration.

Recommendations:

  • Regular maintenance and periodic re-testing should be conducted
  • SCADA and protection relay settings must be continuously monitored
  • Spare parts and contingency plans should be available for critical components

This pre-commissioning test procedure is essential for compliance with SEC regulations and ensures a robust transmission system.