Electrical Partial Discharge (PD) testing is a critical part of ensuring the safety and reliability of high-voltage equipment, such as transformers, generators, and switchgear. During an interview for a position involving PD testing or analysis, you may be asked a variety of technical and practical questions. Below are some common interview questions related to partial discharge and suggested answers.

1. What is Partial Discharge (PD)?

Answer: Partial Discharge is a localized electrical discharge that only partially bridges the insulation between conductors. It occurs when there is a high-voltage stress within the insulation system, causing small discharges in localized areas. PD is an indicator of insulation deterioration, which can lead to complete breakdown over time if not addressed.

2. What are the main causes of Partial Discharge?

Answer: PD can be caused by a variety of factors, including:

  • Voids or air bubbles within the insulation material
  • Defects or impurities in insulation
  • Sharp edges or points that increase the local electric field
  • Surface contamination or tracking
  • Degradation due to aging, mechanical stress, or moisture

3. What are the different types of Partial Discharge?

Answer: There are several types of PD, including:

  • Internal discharge: Occurs within voids or cavities inside solid insulation.
  • Surface discharge: Occurs across the surface of the insulation material.
  • Corona discharge: Occurs in the air surrounding a conductor, usually around sharp points or edges.
  • Treeing discharge: Results in progressive erosion in insulation, leading to branching patterns.

4. Why is Partial Discharge dangerous for electrical equipment?

Answer: PD can progressively degrade the insulation over time, leading to complete insulation failure. This can cause catastrophic failures such as short circuits, equipment damage, or even fires. PD is also an early indicator of developing insulation issues, allowing for preventive maintenance if detected early.

5. How is Partial Discharge detected?

Answer: PD can be detected using several methods, including:

  • Ultrasonic detection: Measures sound waves generated by PD.
  • Electromagnetic detection: Detects radio frequency signals produced by PD.
  • Capacitive couplers: Measures high-frequency pulses associated with PD.
  • Optical sensors: Detects light emissions from PD.
  • Time-domain reflectometry: Locates PD by analyzing the time delay of reflected pulses.

6. What is the significance of PDIV (Partial Discharge Inception Voltage) and PDEV (Partial Discharge Extinction Voltage)?

Answer:

  • PDIV: The voltage at which partial discharge starts to occur. It provides insights into the condition of insulation and how much voltage the equipment can handle before PD begins.
  • PDEV: The voltage at which partial discharge stops occurring. If PDEV is close to the operating voltage, it indicates the presence of persistent PD, which can be harmful over time.

7. What are some common techniques used for partial discharge analysis?

Answer:

  • Phase Resolved Partial Discharge (PRPD) pattern analysis: Involves measuring the PD signals concerning the phase of the applied voltage. PRPD patterns help classify the type of PD.
  • Time domain analysis: Evaluates PD pulse characteristics, such as rise time, pulse width, and magnitude.
  • Frequency domain analysis: Analyzes the frequency content of PD signals to differentiate between types of discharge.

8. What standards are used in Partial Discharge testing?

Answer: PD testing is regulated by several international standards, such as:

  • IEC 60270: This standard defines the basic requirements for PD measurements on electrical apparatus.
  • IEEE 400.3: Guides partial discharge testing in shielded power cable systems.
  • IEC 60034-27: Focuses on partial discharge detection in rotating machines.

9. What equipment is typically used for PD testing?

Answer: PD testing equipment includes:

  • PD detectors: For detecting and measuring PD activity.
  • Couplers or sensors: Capacitive, inductive, or acoustic sensors used to detect PD signals.
  • Oscilloscopes or spectrum analyzers: Used for detailed analysis of PD signals.
  • High-voltage sources: Required to apply the test voltage to the equipment.

10. How can Partial Discharge be prevented or minimized?

Answer: To prevent or minimize PD, the following measures can be taken:

  • Ensuring proper design and manufacturing processes to avoid voids and impurities in insulation.
  • Using high-quality insulation materials resistant to moisture and contamination.
  • Avoiding sharp edges or points in conductors to reduce high local electric fields.
  • Regular maintenance and inspection to detect and address developing PD issues early.

11. How is Partial Discharge related to equipment aging?

Answer: Partial Discharge is both a cause and a symptom of insulation aging. As equipment ages, its insulation deteriorates, making it more prone to PD. At the same time, continuous PD activity accelerates the aging process, leading to further degradation.

12. What are some challenges in Partial Discharge testing?

Answer: Challenges in PD testing include:

  • Background noise: External electrical noise can interfere with PD signal detection.
  • Location of PD sources: Pinpointing the exact location of PD within large equipment can be difficult.
  • Discriminating between different types of PD: Accurately identifying the nature and severity of PD requires expert analysis.

13. How do you interpret the results of a PD test?

Answer: Interpretation of PD test results involves looking at:

  • PD magnitude: The size of the discharge, usually measured in picocoulombs (pC).
  • PD count: The frequency of PD events over time.
  • PRPD patterns: Used to identify the type of PD and its location within the insulation. Analyzing trends over time is also crucial, as increasing PD activity typically indicates worsening insulation conditions.

14. What role does PD testing play in predictive maintenance?

Answer: PD testing is a vital part of predictive maintenance. By monitoring PD activity over time, maintenance teams can predict when insulation failure might occur and perform preventive repairs or replacements before major failures happen.


These are some typical questions and answers that may be encountered during an interview for a role involving partial discharge testing or analysis. Understanding the theory and practical applications of PD testing is essential for professionals in the electrical engineering and high-voltage equipment fields.

Here’s a comprehensive guide to Electrical Partial Discharge (PD) Test Transformer Interview Questions and Answers that might help you prepare for an interview. The questions generally assess both your technical knowledge and practical experience with PD testing and transformers.

General Questions

  1. What is Partial Discharge (PD)?

    • Answer: Partial Discharge is a localized electrical discharge that occurs within a small portion of a solid or liquid dielectric insulation system under high voltage stress. It can occur at points where the electric field strength exceeds the breakdown strength of the insulating material but does not cause a complete breakdown of the insulation.
  2. Why is Partial Discharge Testing Important for Transformers?

    • Answer: PD testing is crucial for transformers because it helps identify potential defects in insulation before they lead to catastrophic failures. Detecting PD early can prevent transformer breakdowns, reduce maintenance costs, and increase equipment longevity.
  3. What are the common causes of Partial Discharge in transformers?

    • Answer: Common causes include insulation defects such as voids, cracks, impurities in insulation material, poor installation, contamination, or mechanical damage.
  4. What are the different types of Partial Discharges?

    • Answer:
      • Internal Discharge: Occurs within the bulk of the insulating material (voids, cracks).
      • Surface Discharge: Takes place at the surface of insulation in air.
      • Corona Discharge: A form of discharge around sharp edges in gas.
      • Treeing: A type of PD that propagates through insulation in a branching pattern.
  5. What are the main methods to detect Partial Discharge?

    • Answer:
      • Ultrasonic Detection: Detects sound waves produced by PD.
      • Electrical Detection: Measures PD current or voltage in high-voltage circuits.
      • Optical Detection: Detects light emitted during a PD event.
      • Chemical Analysis: Dissolved gas analysis (DGA) detects gases generated by PD activity in oil-filled transformers.

Technical Questions

  1. How does a Partial Discharge Test work on transformers?

    • Answer: A Partial Discharge test applies high voltage to the transformer’s insulation system. By monitoring the high-frequency signals emitted from discharges, PD activity can be detected and localized. Measurements are often taken with sensors like capacitive or inductive couplers.
  2. What equipment is used in Partial Discharge Testing for transformers?

    • Answer:
      • PD detectors or measurement systems.
      • High-voltage test transformers.
      • Coupling capacitors or impedance for measuring PD signals.
      • Oscilloscope or PD monitoring equipment to analyze signals.
  3. How do you interpret Partial Discharge test results?

    • Answer:
      • Phase Resolved PD Pattern (PRPD): Helps in distinguishing the type of discharge based on phase-resolved patterns.
      • Magnitude and Frequency: The higher the magnitude and frequency of discharges, the more severe the defect.
      • Trend Analysis: Increasing PD activity over time can indicate worsening insulation conditions.
  4. What are acceptable PD levels for transformers?

    • Answer: Acceptable PD levels vary based on transformer type and voltage class. Typically, for large power transformers, PD levels below 100 picocoulombs (pC) are considered safe, but this can depend on the specific application and insulation design.
  5. How do you locate the source of Partial Discharge in a transformer?

    • Answer: The source of PD can be located using multiple methods:
      • Time-of-Flight Method: By measuring the time it takes for the PD signal to travel, you can locate the source.
      • Ultrasonic Measurements: Pinpoint the source by detecting sound waves.
      • Electromagnetic Sensors: Map the PD activity within the transformer.
  6. What standards govern Partial Discharge testing for transformers?

    • Answer: The most common standards are:
      • IEC 60270: Provides methods for PD measurement and analysis.
      • IEEE C57.113: Guidelines for PD testing in transformers.
      • IEC 60076: Transformer standards include PD testing requirements.

Practical Experience Questions

  1. Have you performed PD testing in the field? What steps did you take?

    • Answer: Explain the practical steps of preparing a transformer for testing, including isolating the transformer, setting up sensors and measurement equipment, applying test voltage, and analyzing PD signals.
  2. How do you mitigate or prevent Partial Discharge in transformers?

    • Answer: You can mitigate PD by ensuring proper insulation design, eliminating sharp edges or points within the transformer, using high-quality insulating materials, ensuring proper drying of insulation (for oil-filled transformers), and preventing contamination during manufacturing or installation.
  3. What are the challenges you have faced during PD testing, and how did you overcome them?

    • Answer: Provide examples such as background noise affecting measurements or difficulty in locating the discharge source, and how you resolved these issues (e.g., filtering noise, using advanced signal processing techniques).

Advanced Questions

  1. What are the limitations of Partial Discharge testing?

    • Answer:
      • PD testing may not detect all types of defects, especially if the defect does not produce significant discharge.
      • External noise can interfere with measurements.
      • In some cases, PD activity may not directly correlate to an imminent failure, leading to difficulty in making maintenance decisions.
  2. Explain how Partial Discharge can evolve into a transformer failure.

    • Answer: Over time, Partial Discharge can degrade the insulation, leading to the formation of electrical trees, which grow and weaken the insulation further. This can cause a full electrical breakdown, leading to transformer failure.
  3. How do modern technologies (like artificial intelligence or machine learning) assist in Partial Discharge analysis?

    • Answer: AI and ML can assist in pattern recognition for classifying different types of PDs, trend analysis for predicting insulation failure, and automated detection to reduce human error and improve diagnosis speed.
  4. What is the difference between online and offline Partial Discharge testing?

    • Answer:
      • Online Testing: Performed while the transformer is in service. It is less invasive and monitors PD in real-time.
      • Offline Testing: Performed with the transformer out of service. It allows for higher voltage stress testing and more accurate detection but requires a system outage.

By preparing answers to these questions, you’ll have a strong foundation for addressing various technical and practical aspects of Partial Discharge testing during a transformer-related interview.

Here’s a comprehensive guide to Electrical Partial Discharge (PD) Test Transformer Interview Questions and Answers that might help you prepare for an interview. The questions generally assess both your technical knowledge and practical experience with PD testing and transformers.

General Questions

  1. What is Partial Discharge (PD)?

    • Answer: Partial Discharge is a localized electrical discharge that occurs within a small portion of a solid or liquid dielectric insulation system under high voltage stress. It can occur at points where the electric field strength exceeds the breakdown strength of the insulating material but does not cause a complete breakdown of the insulation.
  2. Why is Partial Discharge Testing Important for Transformers?

    • Answer: PD testing is crucial for transformers because it helps identify potential defects in insulation before they lead to catastrophic failures. Detecting PD early can prevent transformer breakdowns, reduce maintenance costs, and increase equipment longevity.
  3. What are the common causes of Partial Discharge in transformers?

    • Answer: Common causes include insulation defects such as voids, cracks, impurities in insulation material, poor installation, contamination, or mechanical damage.
  4. What are the different types of Partial Discharges?

    • Answer:
      • Internal Discharge: Occurs within the bulk of the insulating material (voids, cracks).
      • Surface Discharge: Takes place at the surface of insulation in air.
      • Corona Discharge: A form of discharge around sharp edges in gas.
      • Treeing: A type of PD that propagates through insulation in a branching pattern.
  5. What are the main methods to detect Partial Discharge?

    • Answer:
      • Ultrasonic Detection: Detects sound waves produced by PD.
      • Electrical Detection: Measures PD current or voltage in high-voltage circuits.
      • Optical Detection: Detects light emitted during a PD event.
      • Chemical Analysis: Dissolved gas analysis (DGA) detects gases generated by PD activity in oil-filled transformers.

Technical Questions

  1. How does a Partial Discharge Test work on transformers?

    • Answer: A Partial Discharge test applies high voltage to the transformer’s insulation system. By monitoring the high-frequency signals emitted from discharges, PD activity can be detected and localized. Measurements are often taken with sensors like capacitive or inductive couplers.
  2. What equipment is used in Partial Discharge Testing for transformers?

    • Answer:
      • PD detectors or measurement systems.
      • High-voltage test transformers.
      • Coupling capacitors or impedance for measuring PD signals.
      • Oscilloscope or PD monitoring equipment to analyze signals.
  3. How do you interpret Partial Discharge test results?

    • Answer:
      • Phase Resolved PD Pattern (PRPD): Helps in distinguishing the type of discharge based on phase-resolved patterns.
      • Magnitude and Frequency: The higher the magnitude and frequency of discharges, the more severe the defect.
      • Trend Analysis: Increasing PD activity over time can indicate worsening insulation conditions.
  4. What are acceptable PD levels for transformers?

    • Answer: Acceptable PD levels vary based on transformer type and voltage class. Typically, for large power transformers, PD levels below 100 picocoulombs (pC) are considered safe, but this can depend on the specific application and insulation design.
  5. How do you locate the source of Partial Discharge in a transformer?

    • Answer: The source of PD can be located using multiple methods:
      • Time-of-Flight Method: By measuring the time it takes for the PD signal to travel, you can locate the source.
      • Ultrasonic Measurements: Pinpoint the source by detecting sound waves.
      • Electromagnetic Sensors: Map the PD activity within the transformer.
  6. What standards govern Partial Discharge testing for transformers?

    • Answer: The most common standards are:
      • IEC 60270: Provides methods for PD measurement and analysis.
      • IEEE C57.113: Guidelines for PD testing in transformers.
      • IEC 60076: Transformer standards include PD testing requirements.

Practical Experience Questions

  1. Have you performed PD testing in the field? What steps did you take?

    • Answer: Explain the practical steps of preparing a transformer for testing, including isolating the transformer, setting up sensors and measurement equipment, applying test voltage, and analyzing PD signals.
  2. How do you mitigate or prevent Partial Discharge in transformers?

    • Answer: You can mitigate PD by ensuring proper insulation design, eliminating sharp edges or points within the transformer, using high-quality insulating materials, ensuring proper drying of insulation (for oil-filled transformers), and preventing contamination during manufacturing or installation.
  3. What are the challenges you have faced during PD testing, and how did you overcome them?

    • Answer: Provide examples such as background noise affecting measurements or difficulty in locating the discharge source, and how you resolved these issues (e.g., filtering noise, using advanced signal processing techniques).

Advanced Questions

  1. What are the limitations of Partial Discharge testing?

    • Answer:
      • PD testing may not detect all types of defects, especially if the defect does not produce significant discharge.
      • External noise can interfere with measurements.
      • In some cases, PD activity may not directly correlate to an imminent failure, leading to difficulty in making maintenance decisions.
  2. Explain how Partial Discharge can evolve into a transformer failure.

    • Answer: Over time, Partial Discharge can degrade the insulation, leading to the formation of electrical trees, which grow and weaken the insulation further. This can cause a full electrical breakdown, leading to transformer failure.
  3. How do modern technologies (like artificial intelligence or machine learning) assist in Partial Discharge analysis?

    • Answer: AI and ML can assist in pattern recognition for classifying different types of PDs, trend analysis for predicting insulation failure, and automated detection to reduce human error and improve diagnosis speed.
  4. What is the difference between online and offline Partial Discharge testing?

    • Answer:
      • Online Testing: Performed while the transformer is in service. It is less invasive and monitors PD in real-time.
      • Offline Testing: Performed with the transformer out of service. It allows for higher voltage stress testing and more accurate detection but requires a system outage.

By preparing answers to these questions, you’ll have a strong foundation for addressing various technical and practical aspects of Partial Discharge testing during a transformer-related interview.

When interviewing for positions related to High Tension Vacuum Circuit Breaker (HT VCB) panels, particularly concerning electrical partial discharge (PD) and the workings of the system, interviewers often ask a variety of technical and practical questions. These questions help gauge the candidate’s understanding of the equipment, its maintenance, and diagnostic processes. Below are some common interview questions and suggested answers.

1. What is Partial Discharge (PD)?

Answer: Partial discharge is a localized electrical discharge that only partially bridges the insulation between conductors and can occur at any point in the insulation system of high-voltage equipment. It is a sign of degradation in the insulation and can lead to equipment failure if not detected and corrected.

2. How does Partial Discharge occur in a HT VCB Panel?

Answer: Partial discharge in HT VCB panels occurs due to defects in insulation such as voids, surface tracking, or contamination. These defects create localized stress concentrations that cause small electrical discharges within the insulation, weakening the material over time.

3. What are the main causes of Partial Discharge?

Answer:

  • Voids or Gaps in the insulation material
  • Surface contamination or tracking on insulating surfaces
  • Sharp edges or protrusions in the equipment
  • Aging of insulation material
  • Loose connections or poor installation practices

4. How can Partial Discharge in VCB panels be detected?

Answer: Partial discharge can be detected using various methods, such as:

  • Ultrasonic detection: This method picks up the sound emitted by PD activity.
  • Electromagnetic measurement: PD emits electromagnetic waves that can be detected.
  • Thermal imaging: Heat generated by partial discharge can be captured using infrared thermography.
  • Capacitance and current measurements: Specialized sensors measure fluctuations in voltage or current that indicate PD activity.

5. What are the impacts of Partial Discharge if left untreated?

Answer: If partial discharge is not detected and corrected, it can lead to:

  • Insulation degradation
  • Failure of the HT VCB panel, causing unplanned outages
  • Safety hazards such as arc flash incidents
  • Increased maintenance and repair costs
  • Reduced operational life of the equipment

6. What is the significance of PD measurement in HT VCB Panels?

Answer: PD measurement is crucial because it allows for early detection of insulation problems, helping prevent catastrophic failures. It is part of a condition-based maintenance strategy that improves the reliability and longevity of high-voltage equipment.

7. What are the testing standards for Partial Discharge in HT panels?

Answer: Common standards for partial discharge testing in HT VCB panels include:

  • IEC 60270 for PD measurement
  • IEC 62271-200 for VCB panels that include insulation and PD requirements
  • IEEE 400 series standards for PD in high-voltage equipment

8. What preventive measures can be taken to avoid Partial Discharge in HT VCB Panels?

Answer:

  • Regular maintenance and inspection of the insulation
  • Proper installation and adherence to design specifications
  • Periodic testing for early detection of PD activity
  • Ensuring cleanliness of the panel to avoid surface contamination
  • Proper grounding and shielding of electrical components to reduce stress on insulation

9. Can you explain the role of a Vacuum Circuit Breaker (VCB) in an HT system?

Answer: A VCB is used to interrupt electrical current flow by creating and extinguishing an arc in a vacuum environment. The vacuum ensures minimal dielectric breakdown and quickly extinguishes the arc. VCBs are commonly used in HT systems for their high reliability, compact size, and minimal maintenance needs.

10. What safety protocols should be followed during PD testing in HT VCB panels?

Answer:

  • Ensure proper grounding of test equipment.
  • De-energize the panel before opening or conducting tests.
  • Wear appropriate PPE (Personal Protective Equipment), such as insulating gloves and arc flash suits.
  • Isolate the area and restrict access during testing.
  • Use non-contact testing methods where possible to avoid direct exposure to high voltage.

11. What kind of maintenance is required for HT VCB panels to prevent Partial Discharge?

Answer:

  • Regular cleaning of insulating surfaces to remove dust, dirt, or contaminants.
  • Tightening connections to avoid loose parts that can cause PD.
  • Visual inspections for signs of wear, corrosion, or abnormal conditions.
  • Thermal scanning to detect heat spots caused by PD.
  • Electrical testing, such as insulation resistance tests and PD measurements.

12. What is the role of insulation in preventing Partial Discharge?

Answer: Insulation in HT VCB panels prevents electrical contact between conductive parts and confines the electrical field. High-quality insulation helps to minimize the risk of partial discharge by providing a uniform electric field and reducing stress concentrations.

13. What is the typical frequency of PD testing in HT VCB panels?

Answer: The frequency of PD testing depends on the criticality of the equipment, environmental conditions, and historical performance. Typically, PD testing is conducted during annual maintenance or more frequently if the system is older or exposed to harsh conditions.

14. Can you explain the difference between Online and Offline PD Testing?

Answer:

  • Online PD testing is conducted while the system is in operation, allowing for real-time monitoring without shutting down the equipment.
  • Offline PD testing requires de-energizing the system, and it is usually conducted during maintenance or scheduled shutdowns to give a detailed condition assessment.

15. How does aging affect Partial Discharge activity in HT panels?

Answer: As insulation materials age, they lose their dielectric properties, become brittle, and develop micro-cracks or voids. These defects increase the likelihood of partial discharge activity, leading to further degradation and potential failure over time.

Final Thoughts

In an interview setting, understanding the concepts of partial discharge, maintenance procedures, testing methodologies, and safety practices related to HT VCB panels is essential. Being well-prepared to discuss specific examples from your past experience and demonstrating a solid understanding of how to detect, prevent, and mitigate partial discharge issues will help you stand out in these technical interviews.