Contents
Page
1.0
OBJECTIVE
1
2.0
SCOPE
3.0
HANGLING AND STORAGE
4.0
WORK METHODLOGY
4.1
Rigid Coupling
4.2
Mechanical T Installation
4.3
Flexible Coupling Installation
4.4
Drop In Anchor Installation
4.5
Pipe Hanger Installation
4.6
Flanged Fittings Installation
4.7
Valve with Screw Connection Installation
4.8
Valve with Flanged End Connection Installation
4.9
Flow Switch Installation
4.10 Screw Fittings Installation
4.11 Sprinkler Head (with ceiling) Installation
4.12 Sprinkler Head (without ceiling) Installation
4.13 Pipe Sleeve Installation
4.14 Fire Protection Riser Pipe Installation
4.15 Black Pipe Painting
4.16 Black Pipe (with Undercoat) Painting
4.17 Galvanized Pipe Painting
4.18 Fire Pump Installation
4.19 FE-13 System Installation
4.20 NAF SIII System Installation
4.21 Fire Seal installation
4.22 Fireman Intercom System Installation
4.23 Fire Alarm Conduits Installation
5.0
HEALTH, SAFETY, SECURITY AND ENVIRONMENT
6.0 LIST OF ATTACHMENTS
7.0
INSPECTION AND TESTING
8.0
LIST OF APPENDICES
9.0
LIST OF ATTACHMENTS
1.0
OBJECTIVE
This method statement is to describe s the method of which the installation
of Fire Protection Services Installation is carried out for this project.
SCOPES
This procedure applies to project site, which requires Fire Protection Services
installation work, which is carried out by the company.
HANDLING AND STORAGE
PRE- DELIVERY AND STORAGE PREPARATION.
a. Prepare delivery schedule and check site conditions as well as storage
capacity.
b. Prior to delivery of Material to site, a site survey and make all necessary
co-ordination with the main contractor as regards to access for the save
transportation of the said material to the designated location.
c. Coordinate with site workers responsible for the system installation.
3.2. INCOMING STORAGE AT SITE.
a. Check model and type of material against delivery order.
b. Check any damage during transportation.
c. If there is any evidence of damage, an internal inspection shall be made
together with supplier’s representative and the Consultant. A report shall
be submitted to the Consultant on completion of such inspection.
d. Route identification and marking work shall not be started until
coordinates with other Mechanical and Electrical Services.
e. Minor deviation from the approved construction drawing and M&E
drawing would be determined on site with the consent of consultant site
staff.