Transformer Sizing and Selection

Transformer Sizing and Selection 

Step 1: Find the Total Connected Load
Formula:

Total Connected Load (kW) = Sum of 
all individual loads (kW)

Example Calculation:

Lighting load: 30 kW
HVAC load: 50 kW
Machinery load: 70 kW
Other equipment load: 20 kW
Total Connected Load = 30 + 50 + 70 + 20 = 170 kW

Step 2: Add Extra Load for Future Expansion
Formula: 

Total Load with Future Expansion 
(kW) = Total Connected Load x (1 + Future 
Expansion Percentage)

Example Calculation:

Assume a 15% future expansion load
Total Load with Future Expansion = 170 x (1 + 
0.15) = 170 x 1.15 = 195.5 kW

Step 3: Calculate the Maximum Demand Load
Formula: 

Maximum Demand (kW) = Total Load 
with Future Expansion (kW) x Demand Factor

Example Calculation:

Assume a demand factor of 80%
Maximum Demand = 195.5 x 0.8 = 156.4 kW

Step 4: Calculate the Maximum Demand in 
kVA

Formula: Maximum Demand (kVA) = Maximum Demand (kW) / Power Factor (PF)

Example Calculation:

Assume a power factor of 0.85
Maximum Demand (kVA) = 156.4 / 0.85 ≈ 184 
kVA

Step 5: Determine the Transformer Capacity 
with Efficiency Considerations
Formula:

 Required Transformer Capacity (kVA) 
= Maximum Demand (kVA) / Transformer 
Efficiency

Example Calculation:

Assume a transformer efficiency of 95%
Required Transformer Capacity (kVA) = 184 / 
0.95 ≈ 194 kVA

Step 6: Select the Appropriate Transformer 
Size

Select the closest standard transformer size 
that can handle the calculated load.

Example Calculation:

The calculated transformer capacity is 194 kVA. 

The next standard size available is 250 kVA. 
Thus, a 250 kVA transformer would be chosen.

Summary:

Total Connected Load: 170 kW
Total Load with Future Expansion: 195.5 kW
Maximum Demand (kW): 156.4 kW
Maximum Demand (kVA): 184 kVA
Required Transformer Capacity: 194 kVA
Selected Transformer Size: 250 kVA

*

Post a Comment (0)
Previous Post Next Post